Contractual disputes with Korean vendor Doosan for the 1,320 MW Sipat project may derail state-run NTPC's target of adding 3,300 MW power generation capacity in the current fiscal.The company is unlikely to commission the 1,320 MW Sipat project by March 2010, therefore it (NTPC) would miss the target," a source in the know said. Doosan, the equipment supplier for the project, was demanding 100 per cent increase in the prices, to which NTPC objected, sources said.
|