Project monitor reported that Gail Ltd plans to complete 11 of its exploration and production program in 2010.

These projects are
1. Dahej to Vijaipur pipeline
2. Vijaipur to Dadri pipeline
3. Chainsa-Jhajjar-Bamnoli pipeline
4. Chainsa to Jhajjar spurline (Sultanpur-Neemrana)
5. Jhajjar to Hissar pipeline
6. Dadri to Bhawana pipeline
7. Bhawana to Nangal pipeline
8. Compressor stations at Jhabua (phase I & II)
9. Compressor stations at Vijaipur (phase-I & II)
10. Compressor stations at Kalaras
11. Compressor stations at Chainsa

Sources said that Gail expects to complete all these projects by October 2010.

The details of some of these projects are as under

1. With the additional R-LNG supplied from Petronet LNG terminal at Dahej, Gujarat and other sources like Reliance, the capacity upgradation of the Dahej to Vijaipur pipeline project will meet the additional demand of customers en route the existing DVPL and GREP pipelines.
2. The Vijaipur to Dadri pipeline project, on completion will enhance the capacity of the GREP pipeline system.

3. The Chainsa-Jhajjar-Bamnoli pipeline will supply natural gas from various sources to consumers in Haryana, Rajasthan and Delhi.

4. The Chainsa to Jhajjar spurline project will meet the gas demand of consumers in Haryana and Rajasthan, at various locations like Chopanki, Bhiwadi, Dharuhera, Khushkhera, Neemrana, Gurgaon, Khandsa, Manesar and Banmoli.

5. The Jhajjar to Hissar pipeline will supply natural gas or R-LNG will cater to Jhajjar and Hissar, again in Haryana. Feed to this pipeline will be made through the Chainsa to Jhajjar spurline which is connected to Vijaipur to Dadri at Chainsa near Faridabad.

6. The Dadri to Bhawana pipeline project will supply natural gas mainly to the PPCL-Bawana power plant to meet the power requirements of the NCR for the Commonwealth Games 2010.

7. The Bhawana to Nangal pipeline aims to supply R-LNG to Punjab, Haryana and Uttar Pradesh.

8. The compressor station at Jhabua will cater to gas demand at desired pressure to various customers en route Dadri-Bawana-Nangal and Chainsa-Jhajjar-Hissar pipeline systems and upgrade the DVPL pipeline system.

9. Similarly, the compressor stations at Vijaipur, Kailaras and Chainsa will meet the gas demand of customers of the 2 pipeline systems and also upgrade the GREP pipeline.

No comments:

Economic Event Calendar

Economic Calendar >> Add to your site

Best Mutual Funds

Recent Posts

Search This Blog

IPO's Calendar

Market Screener

Industry Research Reports

NSE BSE Tiker

Custom Pivot Calculator

Popular Posts

Market & MF Screener

Company Research Reports